A solvent-free, plasticiser-free conductive adhesive that carries charge from the vinyl surface to the copper tape and the building earth.

U300D conductive adhesive for ESD flooring in a 20 kg pail

Where it is used

  • Static-dissipative and conductive vinyl sheet or tile.
  • Data centres, electronics assembly, operating theatres, explosive-risk areas.
  • Systems earthed through copper tape laid in the adhesive bed.

Not intended for

  • General-purpose bonding — the conductive filler is only justified where earthing is required.
  • Installations where the earth path is not designed and tested as part of the system.
Typical properties — U300D
TypeSolvent-free, plasticiser-free conductive adhesive with curing and filling fillers
Body resistance≤ 3 × 10⁵ Ω (JC/T 550-2019, antistatic grade)
ColourMilky white to light yellow
Viscosity40,000–55,000 mPa·s
Density1,000 g/L
pH7.4
Tack time10–15 min
Open time10–30 min
Coverage200–250 g/m² (20 L ≈ 80–100 m²)
TrowelA2 or B3 notched trowel
Substrate moisture≤ 4%
Ambient conditions20–25 °C / 48–55% RH; do not install below 5 °C

Typical values, not a specification. Batch values are confirmed on the certificate of analysis.

How to run it

  • Design the earth path first: copper tape layout determines whether the system works.
  • Apply 200–250 g/m² with an A2 or B3 notched trowel — coverage is a specification, not a guideline.
  • Lay the vinyl into wet adhesive within the open time; do not allow the film to skin.
  • Test resistance after cure against the project specification, not just against the product limit.

Questions we get asked

Why does ESD flooring need a conductive adhesive?

The adhesive conducts charge from the vinyl surface down to the copper tape and the building earth. A standard adhesive breaks that path.

How is conductivity specified?

As body resistance ≤ 3 × 10⁵ Ω to JC/T 550-2019, antistatic grade. This is a material value, not the finished-floor resistance.

What coverage should be used?

200–250 g/m². Under-application is the most common cause of a failed earthing test.

Which trowel?

A2 or B3 notched trowel.